PAVING CREW
Joe, Roger, Chad, Jeff , Johnny , James, Jerry, James, Mario

Just a Reminder: DON'T Drive Around ROAD CLOSED Signs!!!


Paving Crew**NEW** Two new paving record days for our paving crew this year...  as we look back on the 2004 paving season the paving crew has accomplished what we used to think of asthe impossible.  Over the last 8 years  the paving crew has made a miraculous  jump from paving just a little over 150 ton per day to a whopping 873 1/2 ton in a day.  

Excellent Job Guys!!!

 

 

Here are just a few of the 30 city street segments we have paved so far this season.

1.  Floyd Ave-Roselle to Fine   136,680sq.ft. 
2. Enslen Ave-Orangeburg to Coleman Ct 150,500 sq.ft.
3. Snyder Ave- Bluebird to Dale Rd 87,468 sq. ft.
4. Kst- 6th Street to 9th Street 47,893 sq.ft.
5. Encina Ave- Phoenix to Colfax 64,600 sq.ft.
6. Hackberry Ave- Griswold to the North End 43,461 sq.ft.
7. Colima Ave - All 32,323 sq.ft
8. Marston Way- All 44,000 sq.ft.
9. Redwood Ave- All 21,615 sq.ft.
10. Leon Ave - Tuloumne to Paradise 19,140 sq.ft.
11. Chadwick Ct- All 35,224 sq.ft
12. Alturas Ave- Tuolumne to Paradies 82,83 sq.ft.
     total after 5 months------------>   959,322 sq.ft

Reconstructing entire roads have been our latest and greatest accomplishments.  Our Grinding Crew with our new asphalt grinder can come in and in one day completely remove an entire block of deteriorated asphalt at a depth of 4 to 6  inches. This depth is usually deeper than the existing asphalt, taking out all imperfections.  The very next day the Paving Crew comes in and paves the road back and has the road open usually by 5pm making it accessible to residents coming home from work.  What so many of the residents have experienced is leaving to work with their road in bad shape,  coming home to their street having been completely removed,  leave for work the next day with the road still gone, then coming home from work to a brand new street. 

When the Streets Division Does an "overlay"  it consists of: send out written notification to businesses and residents describing the work to be done, grinding the curb & gutter to a depth of 2 inches, grind any failed areas in the existing road and replace with new asphalt, lay 2 inches of new asphalt over the existing road with our paving machine, and roll for compaction. 


Check out our other pages:  Home | Patching | Paving |  Grinding | Service Request Form


1010 10th Street, Modesto, CA  95354  bullet  P.O. Box 642, Modesto, CA  95353  bullet (209) 577-5200
Technical questions or website bugs may be addressed to webmaster@modestogov.com
City of Modesto Online Privacy and Use Statement