PAVING CREW
Joe, Roger, Chad, Jeff ,
Johnny , James, Jerry, James, Mario
|
|
|
|
**NEW**
Two new paving record days for our paving crew this year...
as we look back on the 2004 paving season the paving crew has accomplished what
we used to think of asthe impossible. Over the last 8 years
the paving crew has made a miraculous jump from paving just a little over
150 ton per day to a whopping 873 1/2 ton in a day.
Excellent
Job Guys!!!
Here are just a few of the 30 city street
segments we have paved so far this
season.
| 1. |
Floyd
Ave-Roselle to Fine |
136,680sq.ft. |
|
2. |
Enslen Ave-Orangeburg
to Coleman Ct |
150,500 sq.ft. |
|
3. |
Snyder Ave- Bluebird
to Dale Rd |
87,468 sq. ft. |
|
4. |
Kst- 6th Street to
9th Street |
47,893 sq.ft. |
|
5. |
Encina Ave- Phoenix
to Colfax |
64,600 sq.ft. |
|
6. |
Hackberry
Ave- Griswold to the North End |
43,461 sq.ft. |
|
7. |
Colima Ave - All |
32,323 sq.ft |
|
8. |
Marston Way- All |
44,000 sq.ft. |
|
9. |
Redwood Ave- All |
21,615 sq.ft. |
|
10. |
Leon Ave - Tuloumne
to Paradise |
19,140 sq.ft. |
|
11. |
Chadwick Ct- All |
35,224 sq.ft |
|
12. |
Alturas Ave- Tuolumne
to Paradies |
82,83 sq.ft. |
| |
total after 5
months------------> |
959,322 sq.ft |
|
|

Reconstructing
entire roads have been our latest and greatest accomplishments.
Our Grinding Crew with our new asphalt grinder can come in and in one day
completely remove an entire block of deteriorated asphalt at a
depth of 4 to 6 inches. This depth is
usually deeper than the
existing asphalt, taking out all imperfections. The very next
day the Paving Crew comes in and paves the road back and has the
road open usually by 5pm making it accessible to residents coming
home from work. What so many of the residents have experienced
is leaving to work with their road in bad shape, coming home
to their street having been completely removed, leave for work
the next day with the road still gone, then coming home from work to
a brand new street.
When the Streets Division Does an
"overlay" it consists of: send out written notification
to businesses and residents describing the work to be done, grinding the curb &
gutter to a depth of 2 inches, grind any failed areas in the
existing road and replace with new asphalt, lay 2 inches of
new asphalt over the existing road with our paving machine, and roll for
compaction.
|
|
|
|